Project Information
Under direction of DPW, Guerrero Street, from Market to 19th streets, is scheduled to be resurfaced with fresh asphalt, following concrete base repairs, installation of new curb ramps at some intersections and repairs to segments of the median. The contractor will begin renovation at Market Street and work toward 19th Street. Look for No Parking/Tow-Away barricade signs that will be posted on your block at least 72 hours in advance of construction. The signs will display the work days and hours, along with a 24-hour contact number to the contractor.
Project Update
Street resurfacing and related construction completed.
Project Location
Guerrero Street, from Market to 19th streets.
Project Duration
100 Calendar Days
Project Team
Department of Public Works, SFPUC
Contractor
Esquivel Grading & Paving
Contact
Bill Adams
Office of Communications & Public Affairs
415-437-7038